THE PROJECT
Estilo Interiors completed a technically challenging project as the main contractor at Utilita Arena Birmingham. The work involved installing new seating zones and architectural balustrades in two sections of the arena, and four vomitory areas. The upgrade improved audience comfort, safety, and sightlines in one of the UK’s busiest indoor venues.
CLIENT: UTILITA ARENA
PROJECT: JCT CAT B
DURATION: 18 WEEKS
THE WORK
- Formed reinforced concrete slabs and risers, removing sections of existing walls to accommodate new steel frameworks.
- Installed structural steel infills and 8 mm steel plate flooring across AF4 (~40 m²), AF8 (~80 m²), and all vomitory sections; extended stair access per updated plans.
- Applied intumescent coatings to all new steelwork for 60-minute fire protection.
- Installed over 90m of powder-coated steel balustrades for enhanced safety.
- Fitted Evertaut Olympian 520 executive stadium seats with vinyl upholstery and cupholders.
- Laid Altro Reliance vinyl flooring with plywood sub-floors and LED stair nosing for durability and visibility.
- Completed electrical upgrades including exit signage, downlighting, and extensions to the fire alarm system, all fully commissioned.